Westfield To Begin 2026 Paving Program With School-Area Roads First

Mayor Jeremy Berman said about 40 roads are slated for resurfacing, with 16 near schools targeted for this summer.

Westfield's 2026 town-funded paving program is set to begin this week, with about 40 roads scheduled for resurfacing in the coming months, according to Mayor Jeremy Berman.
Westfield's 2026 town-funded paving program is set to begin this week, with about 40 roads scheduled for resurfacing in the coming months, according to Mayor Jeremy Berman. (Town of Westfield)

WESTFIELD, NJ — Westfield's 2026 town-funded paving program is set to begin this week, with about 40 roads scheduled for resurfacing in the coming months, according to Mayor Jeremy Berman.

Berman said 16 of those roads are being prioritized for completion this summer because they are near schools.

"On Aug. 4, our contractor expects to begin milling and paving work on Landsdowne Avenue and a portion of Boulevard (from Clifton to Landsdowne)," Berman said.

Find out what's happening in Westfieldfor free with the latest updates from Patch.

The paving work is part of Westfield's capital budget process and a multi-year road improvements plan, according to the town.

The second round of its road assessment program has been completed.

Find out what's happening in Westfieldfor free with the latest updates from Patch.

According to the town, that data allowed coordination with utility companies on a multi-year resurfacing plan aimed at making paving operations as efficient and cost-effective as possible each year.

The town also urged residents whose streets are on the 2026 paving schedule to consider any projects that would require a road opening before paving is finished.

Generator installation and switching from oil to gas are examples of projects that may involve opening the roadway.

According to the town, property owners who wait until after paving is completed could face a substantial fee if the road has to be opened later.

Residents with questions about timing are asked to contact the Engineering Office at 908-789-4100, ext. 4600.

See the full list of roads below:

2026 Anticipated Road Improvements - Work Performed by the Town

StreetLimit of Work
Woodmere DriveEntire length
Fairhill RoadEntire length
Fairhill DriveEntire length
Gallows Hill RoadEntire length
Morris AvenueEntire length
Tice PlaceLower Genesee to Sandy Hill
Sandy Hill RoadEntire length
Summit CourtRahway to Summit Ave
Bell DriveArthur to Dead End
Summit AvenueSummit Court to Clover
Hyslip AvenueEdgar to Warren
First StreetHyslip to Scotch Plains Ave
Dorian RoadLamberts Mill to Scotch Plains
St. John's PlaceEntire length
St Georges PlaceEntire length
Highgate AvenueEntire length
Dorian PlaceEntire length
Osborn AvenueCumberland to Downer
Harrow RoadEntire length
Oxford TerraceEntire length
Pearl StreetEntire length
Azalea TrailEntire length
Windsor AvenueGrandview to South Ave
Boynton AvenueDead end to Roger
Nevada StreetWyoming to Dakota
Roger AvenueEntire length
Massachusetts StreetEntire length
Delaware StreetEntire length
Boynton CourtEntire length
Mountainview TerraceEntire length
Talcott RoadEntire length
Brightwood AvenueEntire length
Clark StreetBrightwood to Dudley
Effingham PlaceEntire length
Stanmore RoadEntire length
Sycamore StreetCentral to Columbus
Coolidge StreetBenson to Salter
Dorian RoadHyslip to Trinity
Landsdowne AvenueEntire length
BoulevardClifton to Landsdowne
Winyah AvenueNorth Chestnut to Linden
Harding StreetSherman to dead end
Tuttle Parkway bridgeNorth to South Avenue
Rahway Avenue*Codding to Willow Grove
Elm Street*East Broad to Dudley
*Funded by 2025 NJDOT State Aid