General Construction Impacts:
Walsh Construction and their sub-contractors will be working around the clock throughout the week at various locations and neighborhoods adjacent to the six-mile construction area will experience general construction noise. Noise may include heavy equipment, lights (at night), vehicle-mounted safety lights (at all times), and backup alarms. All efforts are being taken to limit the impacts to the adjacent communities; however, night work is going to occur as needed and the PTC will not limit the contractor’s hours of operation.
Plymouth Township Roadwork:
Road work will take place on the following roadways between 7 a.m. and 6:30 p.m., Monday through Friday: Walton Rd., Apollo Rd., Township Line Rd.
Road work will take place on the following roadways around the clock from Monday through Friday: Jocelyn Rd., Hickory Rd.
Find out what's happening in Plymouth-Whitemarshfor free with the latest updates from Patch.
Structure work:
24-hour: Hickory Rd. mainline bridge
Retaining walls:
Find out what's happening in Plymouth-Whitemarshfor free with the latest updates from Patch.
- 24-hour: Jocelyn Rd., Hickory Rd., Walton Rd., Fountain Rd., Allandale Rd., Colton Dr., Loretta Ln., Timberfare Cr., Beacon Hill Cir., Jolly Rd.