Traffic & Transit

Highway 6 Culvert Project Delayed Again In Wright County

'We thank you in advance for your patience and understanding while this County Ditch 10 Improvement work is being completed.'

June 4, 2021

A Message from the Wright County Highway Department

Find out what's happening in St. Michaelfor free with the latest updates from Patch.

The County Highway 6 closure in Victor Township will be extended for the County Ditch 10 improvement work by Molnau Trucking, LLC. Originally expected to be open to traffic by the end of the day on Monday, May 17, the time frame for the work has been extended due to recent rains and private utility relocation delays.

Due to the unexpected proximity of private utilities to the culvert, the utility companies will need time to relocate their facilities to accommodate the work.

Find out what's happening in St. Michaelfor free with the latest updates from Patch.

It is the goal to have the culvert work completed and the Highway 6 closure removed by mid to late June (weather permitting).

There is a detour route posted, please follow the posted detour route. If you have any questions or would like additional information on this County Ditch 10 Improvement project, please call one of the following:

  • Matt Detjen, Wright County Ag. & Drainage Coordinator at (763) 682-7571
  • Chris Adams, Project Manager - ISG, Inc. at (507) 381-1966
  • Jennifer Rath, Molnau Inc. at (952) 388-3156

We thank you in advance for your patience and understanding while this County Ditch 10 Improvement work is being completed.


This press release was produced by the Wright County Government. The views expressed here are the author’s own.