Politics & Government
Princeton Rejects All Bids For Landfill Repairs, Seeks $1.6M More
8 bids ranged from about $1.7 million to $6 million, well above the town's estimate for fixing the landfill cap.
PRINCETON, NJ — Princeton has rejected all eight bids for repairs at the Princeton Sanitary Landfill and will advertise the project again. Most of the bids came in well above the town’s cost estimate.
The Princeton Council approved the resolution to reject the bids and rebid the project at its Nov. 9 meeting. The council also introduced a $1.6 million bond ordinance to help pay for the work. A public hearing on the ordinance is set for Nov. 23.
The project would fix surface water problems that are damaging the landfill’s cap. Deputy Administrator Deanna Stockton told the council the town is under state orders to make the repairs.
Find out what's happening in Princetonfor free with the latest updates from Patch.
“The municipality has had a notice of violation from DEP to correct surface water impacts to the landfill cap, and we have been working for about eight years to get permits to address this problem,” Stockton said.
“The project would create a berm in one section to keep the water off of the landfill, and then make some repairs to a surface drainage area as well as a side slope of the landfill,” she added.
Find out what's happening in Princetonfor free with the latest updates from Patch.
Stockton said the town ran into problems with the bids it received.
“We had a wide range of prices, and so that’s why we’re asking to reject the bids and go out to bid again,” she said.
The council approved the resolution by voice vote. No council members asked questions or commented.
Princeton advertised the project Sept. 4, with bids originally due Oct. 1, according to a Nov. 4 memo to the council from Stockton and Principal Engineer JP Ricci.
The town has worked with T&M Associates for more than eight years. The firm does the regular landfill inspections the New Jersey Department of Environmental Protection requires and designed the repair plan.
All state and regional permits were secured a few years ago, according to the memo. But Princeton didn’t have enough money in its capital program to cover T&M’s estimate of about $1.8 million until 2026.
During bidding, the town issued four addenda to correct T&M’s plans and specifications and to push back the bid deadline. T&M also raised its cost estimate to about $2.1 million after contractors pointed out needed changes, the memo says.
Eight sealed bids were opened Oct. 20. They ranged from about $1.7 million to $6 million, with most around $3.5 million.
The lowest bidder used an outdated bid price form that had been replaced in one of the addenda, so its bid had to be rejected, according to the memo. The second-lowest bidder made the same mistake.
The third-lowest bidder then filed a protest against the two lower bids. It cited the wrong bid form and an error involving proposed subcontractors.
That left the third-lowest bidder next in line. But its price of $2,746,989.58 was more than the town had available for the project, the memo says.
Town engineers recommended rejecting all bids and starting over, citing problems with the plans, specifications and estimate, as well as the funding shortfall.
$1.6 million bond ordinance
Engineers also asked the council to introduce a new bond ordinance as soon as possible, so the town could award a construction contract within about six weeks of the memo.
Ordinance 2026-35 would appropriate $1.6 million for the design, permitting, construction, inspection and monitoring of remedial work at the landfill. That includes an $80,000 down payment from money already set aside in past budgets. The rest, $1.52 million, would be paid for with bonds or notes.
The extra money would bring the project’s available funding to about $3.5 million, according to the memo.
Up to $300,000 of the total may go toward related costs allowed under state law, such as engineering and legal fees. The ordinance lists the improvement’s useful life as 15 years.
A bond ordinance needs a two-thirds vote of the council to pass. A public hearing and final vote are scheduled for the council’s Monday, Nov. 23 meeting.
Have a correction or news tip? Email sarah.salvadore@patch.com